Ahmed Hassan Bin-Jamil invested in the Dubai Lagoon project in 2006. Schon properties, the developers say that the project will finally be completed in April but this seems unlikely since the development is still an active construction site. Antonie Robertson / The National
Ahmed Hassan Bin-Jamil invested in the Dubai Lagoon project in 2006. Schon properties, the developers say that the project will finally be completed in April but this seems unlikely since the development is still an active construction site. Antonie Robertson / The National

Five years on, investors of Dubai Lagoon still in limbo

Investors have been told the first units will be ready in April, but after waiting five years, some say they are losing hope they will ever get their keys.

DUBAI // Investors who handed over hundreds of thousands of dirhams for property being built around an artificial lagoon fear they will never be able to move in.

The ambitious community was scheduled for completion five years ago but a string of delays left buyers in limbo.

The developer, Schon Properties, now insists Dubai Lagoon – a Dh3 billion affordable housing project – is on track for a building-by-building handover from April.

But investors say this is not the first deadline to be set, and want the Real Estate Regulatory Authority (Rera) to intervene if there are further setbacks.

One buyer, T?S, a Canadian businessman, is paying interest on bank loans for the unfinished property and renting an apartment for his family.

“How can I survive like this?” he asked. He has already paid Dh1 million – half the amount for four apartments, with the remainder due on completion.

“I thought by 2008 I would have my own home,” he added. “We want Rera to set a deadline or cancel the project and refund investors.”

Dubai Lagoon launched in 2005, with the clusters of eight-storey buildings in seven zones at Dubai Investments Park due to be finished by 2008. The delays have been attributed to road widening, the economic downturn and securing utility clearances.

Rera said it was examining Schon’s proposal to allow investors to switch their units in deferred clusters for those being built now.

“It is under review by the Trust Account department,” the authority said. “The developer applied for a new financial proposal to follow up the work and this is under review.

“Rera asked the developer to communicate with investors about the new financial proposal.

“Regarding the commitment of the developer with the investors, these are contractual agreements and both sides have the right to take legal action to make sure all obligations are fulfilled.”

Some buyers have paid further instalments hoping to secure their apartments. The project also attracted investors from Britain and Europe, who were planning to escape winters in a holiday home.

“I have paid more against my better judgment hoping it would help them finish the apartment,” said David, a British financial adviser and frequent visitor to Dubai since his daughter moved here in 2000.

He has paid more than Dh530,000 – 85 per cent of the total cost – for a one-bedroom apartment.

“I used my retirement money to buy this,” he said. “We thought we’d come here for two months [a year]. But it doesn’t look like the first building will be completed in time.”

The vice president of Schon Properties, Danial Schon, said a building would be completed by April.

Work will focus on zone 1, with 442 apartments in eight buildings.

“Now that the real-estate market is looking extremely positive, Dubai Lagoon is moving forward using a building-by-building strategy,” Mr Schon said. “We are 100 per cent committed to this project and delivering to the customers who have been patient and supportive.”

But investors remain disheartened. “They showed us tiling of one washroom but isolated work is not enough,” said Ahmed Hassan, who paid Dh220,000 as part-payment for a one-bedroom apartment.

“They tried to call us to switch payment plans, sign a new contract and give them more money. But no one wants to pay them more.”

Najam, an American who paid Dh423,000 for a flat, said: “If they complete one building at a time, it will take 10 to 12 years. We have written a petition to Rera that Schon should give us a definite completion date. Will it be one to two years? 20 years? 100 years?”

rtalwar@thenational.ae

Back to the top

More articles


Editor's Picks

 Sarah Geronimo. Courtesy: FLASH Entertainment

Sarah Geronimo brings her star power to Abu Dhabi this weekend

Ahead of her Abu Dhabi concert on Thursday night, we take a look at the Filipina singer Sarah Geronimo’s extraordinary career.

 Fatema holds a picture of her son Nurul Karim as she poses for a photograph in front of her slum house in Savar. Fatema lost her son Nurul Karim and her daughter Arifa, who were working on the fifth floor of Rana Plaza when it collapsed on April 24, 2013. All photos Andrew Biraj / Reuters

These women know the real price of cheap high street fashion

Survivors of the world's worst garment factory accident, struggle to rebuild their lives from the rubble of the Rana Plaza collapse as Bangladesh prepares to mark the first anniversary of the disaster.

 Visitors look at the medieval inventor Al Jazari’s water-powered Elephant Clock. The clock is on show at the 1001 Inventions exhibition at Sharjah Expo Centre. Photos Antonie Robertson / The National

1001 Inventions: in praise of Islam’s gifts to the world

Down the centuries, from camera obscura to designing a sail that allowed early seafarers to tack into the wind, Muslim scientists have made many significant contributions to science. Rym Ghazal and Asmaa Al Hameli visit an exhibition in Sharjah that celebrates those contributions

 Mumbai Indians fans cheer they team on the opening match between Mumbai Indians and Kolkata Knight Riders in IPL 2014 at Zayed Cricket Stadium in Abu Dhabi. Ravindranath K / The National

Earn cash back with the IPL cricket in the UAE

Dunia finance promotion allows cricket lovers to earn up to 6 per cent unlimited cash back on any spending they make on a day when an IPL match is played in the UAE.

 Iranian workers at the Iran Khodro auto plant in Tehran on March 18. Maryam Rahmanian for The National

Iran’s love of cars survives devastating sanctions

Sanctions and energy subsidy reductions might have hurt the Iranian automotive industry. But car makers at one factory are still optimistic, Yeganeh Salehi reports from Tehran

 This comparison image shown on Reddit annotated the objects with vehicles from the movies.

Disney confirms that Star Wars: Episode 7 is filming in Abu Dhabi desert

Disney yesterday confirmed that the filming of Star Wars: Episode 7 is taking place in the desert in Abu Dhabi.

Events

To add your event to The National listings, click here

Get the most from The National