Troubled German developer puts Dubai Waterfront towers on hold
Nathalie Gillet
- Last Updated: July 09. 2009 6:30PM UAE / July 9. 2009 2:30PM GMT
Alternative Capital Invest (ACI) Real Estate, the troubled German-owned developer behind projects such as the Boris Becker, Michael Schumacher and Niki Lauda towers, says it will put on hold its developments on the Dubai Waterfront and shift investor holdings to other assets.
Affected projects include the Ferretti and Pershing towers, which have yet to begin construction. The company said it would shift client’s investments in these developments to its towers in Business Bay, which consist mainly of the towers linked to prominent German sport figures. The Becker, Schumacher and Lauda towers are currently under construction but running significantly behind schedule.
In recent weeks a group of German investors in ACI-linked funds, which have financed the developments, complained that the developers have missed payout deadlines. The postponement of the Dubai Waterfront towers comes as ACI is struggling to maintain investor funding that it needs to complete existing projects.
Robin Lohmann, the managing director of ACI Dubai, said in a recent interview slowing payment was having an impact on construction schedules.
“All our sites [in Business Bay] are under construction,” he said. “But since there are delays in people’s payments, we have had to slow down in order to deal with it. If nobody pays, the risk is that construction stops. This is the last thing that we want.”
He added that of the 11 projects the company had underway, at least seven were under construction.
ngillet@thenational.ae
See also
Other Business stories
Your View
- Are you concerned with the standard of education your children receive?
- What would you like to see included in the new law on smoking?
- What can be done to ease the increasing cat population in the UAE?
- Would you hand back Dh5m if you found it in your bank account by mistake?
- What would you like to see in the new code of conduct for schools?
Most popular stories
- The apartheid will end when Israelis have to face its cost
- Dubai Metro's music causes disharmony
- Education faces up to double challenge
- Police raid illegal plastic surgery clinic
- UAE banks’ debt woes to grow
- For Burj refunds, go to Dubai
- New guide to being a better boss
- Hunt for mother of abandoned baby
- Interpol warrant for runaway fraudster
- Faulty lift to blame for Dubai tower shutdown


Added: 07/10/09 06:20:00 PM
Why is robin saying the delay is caused by slow payments ????? everyone that purchased in these towers has paid more than 30% of the full price, and nothing at all has been spent on construction of niki lauda tower.. for 2 years !!!!!!! .....and very little spent on the others ...on which no work is ongoing.... this guy is just stalling ....i am taking them to court at present .
ron oakeley, dubai